logo: RMD Australia

RMD Australia has 17 branches nationwide: 1800 111 763

photo: megashor supporting freeway and road
 

Projects > Roads & Busways > Tiger Brennan Drive

Roads
 
LOCATION: Darwin, Northern Territory.
CLIENT: Macmahon Contractors Pty Ltd
   

Testimonial

I would just like to extend, on behalf of Macmahon and myself, our sincere appreciation your company's support and effort during our Tiger Brennan Drive Bridge Project. Through your assistance we have managed to beat deadline and meet budget. Can you also pass on my thanks to the guys in Adelaide for turning around drawing changes so promptly, to allow us an uninterrupted program. I look forward to working with you on our next Bridge Project.

Yours sincerely

Graham Gust
Project Engineer – Structures
Macmahon Holdings Ltd - NT, Australia


The Tiger Brennan Drive upgrade is currently the largest project underway in Darwin, the project is estimated to cost approximately $400 million by it’s completion in June 2010. This is an exceptionally high profile project and RMD Darwin’s participation is an important step for the Darwin business.

The progress of this project has been monitored by the Darwin sales team for more than 18 months to ensure RMD’s involvement. This commenced in late September 2009 with supply of equipment to RMD’s client, Macmahon Contractors Pty Ltd.

The project consists mainly of road construction, which involves earth works, bitumizing roads and constructing bridges. RMD Darwin will be supplying all the components including shoring, wall formwork, columns, as well as pier supports and headstock formwork for all three bridges being constructed on this project.

The RMD Australia products being hired by Macmahon Contractors are Super Slim Soldiers, Alform Beams, the Rapidshor shoring system and also Rapidstage scaffolding including tube and fitting. Products sold to Macmahon are Rapid Bar Tie, ply, LVL timber beams and special brackets which are being used for the diamond shaped piers required on the cycle bridge component of this construction.

One element of the project is quite unique due to the size of the wall being constructed and because it was not poured in stages. The entire 52m long by 9m high by 400mm thick wall was poured in one operation over an eight hour period.

Macmahon Constructions requirement was to have no horizontal cold joints in the wall, which meant that the wall had to be poured in one continuous operation. The 185m3 concrete was poured by two concrete pumps operating simultaneously, this had to be done to ensure that the concrete at the bottom of the pour didn’t begin curing and hardening before the rest of the pour, creating a substandard finish when the shutters were removed. The RMD Australia Engineering Department ensured this didn’t happen by calculating the pour rates and extra strengthening required for the bottom shutters required to provide consistent curing and provide the client with a class two finish.

The pour was a success with no movement whatsoever in the formwork and it provided an excellent finish.

 

Tiger Brennan Drive

Project Photo:
Tiger Brennan Drive,
Darwin, NT.