| Services
provided by RMD Australia
Extensions to Victoria Point Shopping
Centre amounted to approximately 10,000m² of extra
shops and car parking, which required approximately 4,000m²
of undercroft area for floodwater, approximately 10,000m²
of roof area at a height of 6.5m and approximately 2,500m²
of mezzanine area.
The Rapidshor shoring system was used
with Albeam as primary beams, with a leg grid of 1.8m
x 2.4m. Rapidshor supporting Airodek 3m beams were used
under the deck area, with a 3m x 1.8m leg grid. Swiftform
supplied Hyplank as a working deck on the Rapidshor, which
is easily moved during erection and stripping.
Using RMD Australia equipment allowed
Swiftform to erect the false work extremely quickly. Also,
the supply of Airodek 3m Beams and Albeam as Primary Bearers
negated the need for the client to supply 150 x 77 LVL.
The client also enjoyed excellent turn
around, saving time and labour in the stripping process
because Rapidshor disassembles very quickly.
|