logo: RMD Australia

RMD Australia has 17 branches nationwide: 1800 111 763

photo: super slim soldiers in place as formwork for Olympic Dame mine
 

Projects > Mining > Newman Hub

Mining Shoring and Formwork - RMD Australia
 
LOCATION: Pilbara, WA.
CLIENT: Macmahon Holdings Ltd
   

Testimonial

“Macmahon are working on the Newman Hub mine ore handling facility in the Pilbara and we have been particularly pleased with RMD’s efficient designs and adaptable products which have allowed us to achieve fast construction times. Their products are easy to use, particularly their new Alshor Plus shoring system which has considerably enhanced our productivity on this project.”

Martin Headd
Senior Project Engineer,
Newman Hub MACMAHON

Project Information

BHP Billiton is the World’s largest diversified resources company and owner of Iron Ore operations throughout Western Australia.

As part of its self entitled $1.85 billion Australian dollar ‘Rapid Growth Project 4’, which will increase its Iron Ore mining capacity to 155 million tonnes per year, BHP Billiton awarded the $80 million contract to build a new screening plant, crushing station and coarse ore stockpile facility, to specialist Australian contractor Macmahon Holdings Limited.

The project, that included extensive foundations, a myriad of plinths and bases for conveyors and rail lines, the large scale crushing station and coarse ore stockpile facilities, required the use of formwork and shoring to construct the more than 30,000 cubic metres of structural concrete.

The remote nature of the location of the facilities in the Pilbara region in the North of Western Australia, meant that the movement of equipment to the site required rigorous planning and built in redundancy, in order to ensure work was not interrupted by the need to source equipment from the nearest RMD Australia branch some 1,000 km’s away in Perth.

Commenting on the project RMD Australia Sales Representative, Simon Hastings said: “With any large scale construction programme like the ‘Rapid Growth Project 4’, there are numerous activities taking place at any one time that depend on each other in order for the project to progress.”

Given just seven months to complete the formwork and shoring stages of the project, RMD Australia began work onsite in February 2008, shipping in 200 tonnes of equipment for the project, including Alshor Plus, Megashor, Rapidshor and Rapidstage access scaffold to the site. The main walls were formed using crane handled Super Slim Soldier and Alform beam shutters.
Simon: “In all, the project required the construction of two main structures. The 22.5m by 10.5m ‘Crushing Station’ with walls up to four metres high and 750mm thick and the larger ‘Coarse Ore Stockpile’ building, measuring 65.0m by 10.2m.

“The project was complex with the main challenge being the shoring to the 1500mm thick upper slab in the ‘Coarse Ore Stockpile’. Large cast-in steel chutes, along with 45 degree soffit chamfers on both sides of the internal structure, meant that the design team would need to come up with a design solution that would cater for the integration of cast-in chutes and the concrete slab. “In order to achieve this we designed and manufactured special cranked soldiers to allow support for the 45 degree angles in the upper slab. Thanks to the swift response of our design team and the flexibility of the Rapishor shoring system, we were able to overcome the challenge and complete the final pour to finish the upper slab in mid September 2008 - right on schedule.”

 
Newman Hub Pilbara

Project Photo:
Newman Hub,
Pilbara, WA..